Power Hungry

Except when an event such as the infamous 2003 blackout in the northeast takes place, the nation's electric grid isn't something most of us think much about. But maybe we should.

The 2003 blackout affected an estimated 55 million people in the U.S. and Canada, some of whom went without lights, telephone, transportation, banking, sewage services, and water for days. The cause turned out to be hot summer temperatures and our hunger for more air-conditioning power, which caused a generating plant in Ohio to switch offline putting a strain on overhead transmission lines. Those lines then overheated, expanded and sagged, coming in contact with overgrown trees. In minutes, line after line failed. The cascading effect that resulted ultimately forced the shutdown of more than 100 power plants.

The Department of Homeland Security (DHS), with support from the electric utility industry and the Department of Energy, wants to be prepared for any potential large-scale blackout that could impact the extra high voltage (EHV) transformers. The U.S. electric grid has three main components: generation (creation of electricity), transmission (long haul transport of electricity), and distribution (shorter distances connecting the electricity to the consumer/end user). The electric grid is complex with more connection points than it had even a few years ago. The U.S. has 80,000 miles of extra-high voltage (EHV) transmission lines making up the backbone transmission grid that enables the long-haul transport of electricity for our nation. EHV transformers are critical pieces of equipment on the transmission grid. 90% of consumed power passes through a high voltage transformer at some point.

If these transformers fail, especially in large numbers, therein lies a very big problem.

EHV transformers are huge, weighing hundreds of tons, making them difficult to transport – in some cases specialized rail cars must be used (and there is a limited supply of these). Many of the EHV transformers installed in the U.S. are approaching or exceeding the end of their design lifetimes (approx 30-40 years), increasing their vulnerability to failure. Although the industry does maintain limited spares, the ability to quickly and rapidly replace several transformers at once would still be a challenge. Because of these issues, the need for emergency replacement EHV transformers was identified as a top priority by the Energy Sector.

Transformers are complex systems, and all are custom built. If several transformers were to fail catastrophically, it would be challenging to quickly replace them. Sarah Mahmood, a Department of Homeland Security Science and Technology Directorate (S&T) program manager, is addressing these issues through S&T's "Recovery Transformer (RecX)" program. She is overseeing the design and development of a prototype fast-turnaround EHV transformer scheduled to be tested operationally in March 2012.

"The goal of the spring 2012 exercise is to conduct a full, in-grid, pilot demonstration, including the transportation, delivery, installation, and commissioning of the prototype RecX in a matter of days, not weeks or months, as with traditional EHV transformers." says Mahmood.

The RecX prototype is designed to be modular, smaller and lighter than a traditional transformer, allowing for easier transportation and more rapid installation, enabling faster recovery in the event of an emergency.

Many events could cause such catastrophic failures: terrorism of course, but also such unavoidable events as natural disasters: hurricanes and tornadoes, and even solar plasma flares disrupting Earth's magnetic field.

The RecX is being built by the Electric Power Research Institute's (EPRI) contractor, the ABB Group of St Louis, MO, and, when completed, will be loaded onto a series of tractor-trailers and caravanned to Texas. There it will be installed and commissioned in the CenterPoint Energy grid, outside the Houston area.

"We're very excited about the upcoming pilot demonstration and the opportunity to validate our concept and design," says Mahmood.

Featured

  • ASIS International and SIA Release “Complexities in the Global Security Market: 2024 Through 2026”

    ASIS International and the Security Industry Association (SIA) – the leading security associations for the security industry – have released ”Complexities in the Global Security Market: 2024 Through 2026”, a new research report that provides insights into the equipment, technologies, and employment of the global security industry, including regional market breakouts. SIA and ASIS partnered with global analytics and advisory firm Omdia to complete the research. Read Now

  • President Biden Issues Executive Order to Bolster U.S Port Cybersecurity

    On Wednesday, President Biden issued an Executive Order to bolster the security of the nation’s ports, alongside a series of additional actions that will strengthen maritime cybersecurity and more Read Now

  • Report: 15 Percent of All Emails Sent in 2023 Were Malicious

    VIPRE Security Group recently released its report titled “Email Security in 2024: An Expert Look at Email-Based Threats”. The 2024 predictions for email security in this report are based on an analysis of over 7 billion emails processed by VIPRE worldwide during 2023. This equates to almost one email for everyone on the planet. Of those, roughly 1 billion (or 15%) were malicious. Read Now

  • ASIS Announces ANSI-Approved Cannabis Security Standard

    ASIS International, a leading authority in security standards and guidelines, proudly announces the release of a pioneering American National Standards Institute (ANSI)-approved standard dedicated to cannabis security. This best-in-class standard, meticulously developed by industry experts, sets a new benchmark by providing comprehensive requirements and guidance for the design, implementation, monitoring, evaluation, and maintenance of a cannabis security program. Read Now

Featured Cybersecurity

Whitepapers

New Products

  • EasyGate SPT and SPD

    EasyGate SPT SPD

    Security solutions do not have to be ordinary, let alone unattractive. Having renewed their best-selling speed gates, Cominfo has once again demonstrated their Art of Security philosophy in practice — and confirmed their position as an industry-leading manufacturers of premium speed gates and turnstiles. 3

  • FEP GameChanger

    FEP GameChanger

    Paige Datacom Solutions Introduces Important and Innovative Cabling Products GameChanger Cable, a proven and patented solution that significantly exceeds the reach of traditional category cable will now have a FEP/FEP construction. 3

  • ComNet CNGE6FX2TX4PoE

    The ComNet cost-efficient CNGE6FX2TX4PoE is a six-port switch that offers four Gbps TX ports that support the IEEE802.3at standard and provide up to 30 watts of PoE to PDs. It also has a dedicated FX/TX combination port as well as a single FX SFP to act as an additional port or an uplink port, giving the user additional options in managing network traffic. The CNGE6FX2TX4PoE is designed for use in unconditioned environments and typically used in perimeter surveillance. 3